Meeting: 27/09/2022 - Cabinet (Item 27)

27 Leisure Transformation Programme - Update pdf icon PDF 85 KB

Non-Key Decision

Councillor Rachel Madden – Executive Lead Member for Leisure, Health and Wellbeing

 

Minutes:

Cabinet received a progress update on the implementation of the Leisure Transformation Programme and were requested to consider an additional recommendation to enable future projects/schemes to be delivered in a timelier manner.

 

Members considered the alternative options of not supporting the internal transfer of £0.5m from the Kirkby Leisure Centre budget to the Hucknall

second swimming pool budget and declining to grant delegated authority to facilitate future funding schemes.  Neither options were recommended as the Hucknall Leisure Centre project was due to overspend its budget allowance and delays in adding schemes to the Capital Programme would culminate in future project delays.

 

RESOLVED that

a)    the content of the report be received and noted;

 

b)    the realignment of £0.5m from the Kirkby Leisure Centre capital project code to the Hucknall second swimming pool capital project code, to support the project through to completion, be approved.

 

Reason:

To ensure that Cabinet is updated on progress with delivery of the leisure transformation programme and to enable the Council to facilitate future projects in a timelier manner.